Technical Points for Vacuum Preloading in Large Land Reclamation Projects
The characteristics of vacuum preloading make it very suitable for large-scale dredging and dredging soil-building projects. To make full play of its advantages, it is necessary to closely combine its technical key points with the landfilling and dredging land reclamation project.
1.1 Vacuum preloading block
With the limitations of sealing technology, it is impossible to limit the processing area of a single block. At present, the area of a single block can reach 5*10000 square meters, but according to past experience, it is generally suitable to divide the block by 3*100000 square meters per block. A plurality of single blocks can be combined into one zone, and each can be constructed synchronously. Flowing operations are performed between the zones to reuse the vacuuming equipment and reduce the engineering input. The division of the blocks should be combined with the design load and reinforcement requirements of the site.
1.2 sand cushion
The physical and mechanical properties of the flushed silt produced by landfilling and landing are extremely poor, and the surface of the dredged silt must be treated to ensure the smooth follow-up construction. Before the construction of the sand cushion layer, a layer of geogrid and geotextile can be laid in the area with large sludge content. If the treatment of the geotextile fabric is still carried out, the mulled mud phenomenon may occur, and the 801cm-1m thick medium may be laid first. Fine sand cushion, re-laying, coarse sand cushion, which can guarantee the quality of medium and coarse sand cushion, so that it has good horizontal drainage effect.
For the dredging process, in order to ensure the flatness of the sand cushion layer, an energy-eliminating head should be provided at the outlet of the blow-fill pipeline to reduce the flushing of the pipe head to avoid a large punching hole at the position of the pipe head.
1.3 Insert Plastic Drainage Vertical Drains(PVD Wick Drains)
If the drainage board needs to penetrate the sandy soil that communicates with the outside world, the clay and the content of the clay should be analyzed. If most of the soil samples contain more than 15% of the powder and clay content, and there is cementation, it will not affect the vacuum preloading. Otherwise, the drainage board should be prevented from penetrating the soil layer or other special areas. Reinforcement plan.
1.4 Setting Sealing Wall
Since the construction of each block is carried out, a common sealing wall will appear between the adjacent two reinforcing blocks. During the vacuuming process, the mud particles in the wall will be affected by the soil shrinkage in the reinforcement area. The vacuum pressure is taken away, and the long time will cause the mud mixing pile to lose the sealing effect. For this reason, for the adjacent area where the vacuuming time interval is more than 15d, the common sealing wall should adopt a double-row mud mixing pile with a combination of length and shortness. This problem is solved by increasing the upper width of the wall. The length of the short pile is generally 3-4 meters, and the length of the long pile is determined according to the geological conditions.
1.5 Vacuum Preloading Soft Soil Processing
The filter tube is made of pvc plastic tube, the spacing of the filter tube should not be more than 6.5 meters, the depth of the filter tube is 0.3cm, and the vacuum gauge under the membrane is arranged between the two filter tubes.
The sealing film is made of 2 layers of polyethylene film, the size of which is predetermined according to the plane size of the reinforcement zone. For the adjacent two reinforcement zones, a narrow strip of vacuum film can be pre-buried in the common sealing wall in the later construction area. The remaining membrane joints are then bonded during subsequent construction. The second sealing membrane of the former zone is covered with the upper part of the common sealing wall and bonded to the sealing film of the latter zone to ensure that the sealing wall is sealed during vacuuming. There will be no air leaks.
Vacuum pump-7.5kw is arranged in a set of about 800 square meters, according to the order of motor, water pump, water tank, gate valve, check valve, and film outlet. The joints are sealed with rubber mat, glass glue, etc. The mouth and tank inlets are kept at the same level.
1.6 Water Cover on The Sealing Membrane
Under normal circumstances, the depth of overburden does not exceed 0.5m. It is pointed out in particular that seawater is very cheap and convenient for reclamation land. If the depth of overburden is properly deepened, the construction period can be exchanged at a very low cost. Overburden preloading is gradually being promoted.