Soft Soil Treatment Specialist, China Wick Drains, Prefabricated Vertical Drains
Monday, October 28, 2019
Wednesday, October 23, 2019
Introduction To Non-cushion Sand Layer Vacuum Preloading Method
The method relates to a large area soft ground treatment method, in particular to a vacuum preloading method without a drainage sand layer.
Non-cushion sand layer it includes the following main steps:
1) laying drainage plates on the treatment site according to the plum pile type;
2) arranging the horizontal drainage system to replace the medium coarse sand cushion used in the previous vacuum preloading construction, two kinds of laying can be used One of the ways;
3) Connect the main pipe of the horizontal drainage system to the vacuuming device, and then vacuum the construction after filming.
The vacuum preloading method for the non-drained sand cushion of the invention is suitable for the reinforcement of large-area soft soil foundation, especially for the dredger fill and the newly deposited ultra-soft soil, and the utility model saves a large investment of laying the sand cushion layer. The vacuum transmission effect is good, and the horizontal drainage system of the wire spring tube + tube plate connector + drainage plate can realize large-scale finished product and normalized construction, and the laying time is short, and can be recycled and reused. The construction period is short and the unique advantage of economic saving.
Non-cushion sand layer it includes the following main steps:
1) laying drainage plates on the treatment site according to the plum pile type;
2) arranging the horizontal drainage system to replace the medium coarse sand cushion used in the previous vacuum preloading construction, two kinds of laying can be used One of the ways;
3) Connect the main pipe of the horizontal drainage system to the vacuuming device, and then vacuum the construction after filming.
The vacuum preloading method for the non-drained sand cushion of the invention is suitable for the reinforcement of large-area soft soil foundation, especially for the dredger fill and the newly deposited ultra-soft soil, and the utility model saves a large investment of laying the sand cushion layer. The vacuum transmission effect is good, and the horizontal drainage system of the wire spring tube + tube plate connector + drainage plate can realize large-scale finished product and normalized construction, and the laying time is short, and can be recycled and reused. The construction period is short and the unique advantage of economic saving.
Friday, October 18, 2019
The main purpose of the dredging projects
The main purpose of the dredging project is to excavate the harbor basin, the inbound waterway, etc., to fill the land to build the dock, the port area and the port industrial zone, the coastal city land and recreational land and land reclamation, the shore beach maintenance, the water conservancy and flood control and the reservoir area. Improvement of water environment such as dredging, rivers, lakes and seas, ecological restoration, construction and landfill of various underwater pipelines. The role of dredging projects in human social progress, environmental improvement and economic development is very important.
Use dredging methods to dig shallow sections of deep rivers or bays to improve navigation or flood discharge capacity; an economically viable primary method of landfilling dredged soils in excavation channels or harbor basins into nearby low-lying areas for land reclamation .
Dredging has traditionally been treated in a manner that is abandoned or dumped in the waters adjacent to the project. The dredging project has created a new way of turning waste into treasure and comprehensively processing it, and then developed it into the use of dredged soil as building materials and materials for building buildings. The dredging project is also extended to excavate the bottom of the river or the bottom of the sea to bury the river or cross-sea pipeline (water pipes, oil pipes, transmission cables, communication cables, etc.); remove the sand and stone for hydraulic engineering with strong underwater displacement capacity. Material foundation and soft ground improvement; blowing sand to protect the beach and so on.
In the past few decades, human beings have increasingly demanded environmental standards. Preventing and reducing the pollution of waters and land by dredging activities has become an important issue that must be considered in dredging projects. Dredging methods are used to excavate underwater contaminated soils and carry out engineering. Processing has also become an important part of dredging projects.
Thursday, October 17, 2019
What is Dredging and Its Application
Dredging is to dredge, widen or dig deep waters such as deep rivers and lakes, and use manmade power or machinery to carry out underwater earthwork or excavation works.
The generalized dredging includes the reef and the fried beach, which are carried out by the blasting method under water. A small river that is constructed by artificially breaking the flow. Various dredgers are widely used in mechanical construction, and onshore construction machinery such as rope shovel is sometimes used.
About the dreging history, the mechanical dredging began in 1600, and the prototype of the chain bucket dredger appeared in the construction of the port of Rotterdam, the Netherlands. China began construction of dredgers in the Huangpu River in 1889. In 1929, the Jiangnan Shipyard caused a chain bucket dredger. In the early 1980s, China had an annual capacity of about 300 million cubic meters of mechanical dredging.
Dredging works are widely used: 1, to excavate new waterways, ports and canals. 2, Deep, widen and clean up existing waterways and ports. 3, dredge the rivers, channels, and dredging of the reservoir. 4, Excavation of foundation pits for hydraulic structures such as docks, docks and ship locks. 5, Combine dredging to carry out landfilling, reclamation and other projects. 6, Clear underwater obstacles.
The generalized dredging includes the reef and the fried beach, which are carried out by the blasting method under water. A small river that is constructed by artificially breaking the flow. Various dredgers are widely used in mechanical construction, and onshore construction machinery such as rope shovel is sometimes used.
About the dreging history, the mechanical dredging began in 1600, and the prototype of the chain bucket dredger appeared in the construction of the port of Rotterdam, the Netherlands. China began construction of dredgers in the Huangpu River in 1889. In 1929, the Jiangnan Shipyard caused a chain bucket dredger. In the early 1980s, China had an annual capacity of about 300 million cubic meters of mechanical dredging.
Dredging works are widely used: 1, to excavate new waterways, ports and canals. 2, Deep, widen and clean up existing waterways and ports. 3, dredge the rivers, channels, and dredging of the reservoir. 4, Excavation of foundation pits for hydraulic structures such as docks, docks and ship locks. 5, Combine dredging to carry out landfilling, reclamation and other projects. 6, Clear underwater obstacles.
Tuesday, August 6, 2019
Technical Points for Vacuum Preloading in Large Land Reclamation Projects
The characteristics of vacuum preloading make it very suitable for large-scale dredging and dredging soil-building projects. To make full play of its advantages, it is necessary to closely combine its technical key points with the landfilling and dredging land reclamation project.
1.1 Vacuum preloading block
With the limitations of sealing technology, it is impossible to limit the processing area of a single block. At present, the area of a single block can reach 5*10000 square meters, but according to past experience, it is generally suitable to divide the block by 3*100000 square meters per block. A plurality of single blocks can be combined into one zone, and each can be constructed synchronously. Flowing operations are performed between the zones to reuse the vacuuming equipment and reduce the engineering input. The division of the blocks should be combined with the design load and reinforcement requirements of the site.
1.2 sand cushion
The physical and mechanical properties of the flushed silt produced by landfilling and landing are extremely poor, and the surface of the dredged silt must be treated to ensure the smooth follow-up construction. Before the construction of the sand cushion layer, a layer of geogrid and geotextile can be laid in the area with large sludge content. If the treatment of the geotextile fabric is still carried out, the mulled mud phenomenon may occur, and the 801cm-1m thick medium may be laid first. Fine sand cushion, re-laying, coarse sand cushion, which can guarantee the quality of medium and coarse sand cushion, so that it has good horizontal drainage effect.
For the dredging process, in order to ensure the flatness of the sand cushion layer, an energy-eliminating head should be provided at the outlet of the blow-fill pipeline to reduce the flushing of the pipe head to avoid a large punching hole at the position of the pipe head.
1.3 Insert Plastic Drainage Vertical Drains(PVD Wick Drains)
If the drainage board needs to penetrate the sandy soil that communicates with the outside world, the clay and the content of the clay should be analyzed. If most of the soil samples contain more than 15% of the powder and clay content, and there is cementation, it will not affect the vacuum preloading. Otherwise, the drainage board should be prevented from penetrating the soil layer or other special areas. Reinforcement plan.
1.4 Setting Sealing Wall
Since the construction of each block is carried out, a common sealing wall will appear between the adjacent two reinforcing blocks. During the vacuuming process, the mud particles in the wall will be affected by the soil shrinkage in the reinforcement area. The vacuum pressure is taken away, and the long time will cause the mud mixing pile to lose the sealing effect. For this reason, for the adjacent area where the vacuuming time interval is more than 15d, the common sealing wall should adopt a double-row mud mixing pile with a combination of length and shortness. This problem is solved by increasing the upper width of the wall. The length of the short pile is generally 3-4 meters, and the length of the long pile is determined according to the geological conditions.
1.5 Vacuum Preloading Soft Soil Processing
The filter tube is made of pvc plastic tube, the spacing of the filter tube should not be more than 6.5 meters, the depth of the filter tube is 0.3cm, and the vacuum gauge under the membrane is arranged between the two filter tubes.
The sealing film is made of 2 layers of polyethylene film, the size of which is predetermined according to the plane size of the reinforcement zone. For the adjacent two reinforcement zones, a narrow strip of vacuum film can be pre-buried in the common sealing wall in the later construction area. The remaining membrane joints are then bonded during subsequent construction. The second sealing membrane of the former zone is covered with the upper part of the common sealing wall and bonded to the sealing film of the latter zone to ensure that the sealing wall is sealed during vacuuming. There will be no air leaks.
Vacuum pump-7.5kw is arranged in a set of about 800 square meters, according to the order of motor, water pump, water tank, gate valve, check valve, and film outlet. The joints are sealed with rubber mat, glass glue, etc. The mouth and tank inlets are kept at the same level.
1.6 Water Cover on The Sealing Membrane
Under normal circumstances, the depth of overburden does not exceed 0.5m. It is pointed out in particular that seawater is very cheap and convenient for reclamation land. If the depth of overburden is properly deepened, the construction period can be exchanged at a very low cost. Overburden preloading is gradually being promoted.
Thursday, August 1, 2019
Vacuum Preloading Soft Soil Improvement Technique Application Prospects In Land Reclamation
With the rapid development of our social economy, the land resources available for economic construction in the coastal areas are becoming more and more tense. Therefore, the pace of reclamation and land reclamation is accelerating with the needs of economic development, and its engineering technology is also constantly developing and maturing.
In recent years, there are mainly two ways to reclaim land for land reclamation. One way is to open a mountain for reclamation, and the other is to make land by dredging the dredged soil. The former method is more and more damaging to the environment due to high cost, and its use is increasingly restricted by government departments. The latter method is not only low in cost, relatively environmentally friendly, but also has a short construction period. More importantly, with the increase of port construction, the landfilling of dredged soil can minimize the external throwing of dredged soil in port engineering. While greatly reducing the cost of dredging projects, the use of dredged soil as a reclamation resource, so that the dredged soil that should be discarded has a value, can be described as a multi-pronged.
Because landfilling by dredging and filling land has great advantages in both technical and economic benefits, this land reclamation method is more and more accepted by people and has been widely used in reclamation projects in coastal areas. . This land reclamation method also brings greater application prospects to vacuum pre-loading foundation treatment technology.
The purpose of reclamation is to provide land areas that can be used for economic construction. If the site is to meet the requirements of use, ground treatment must be carried out. Vacuum preloading is widely used in large reclamation projects because the technology has the following characteristics:
1) Save pre-compressed materials and reduce project cost. Vacuum preloading uses atmospheric pressure as the motive force for preloading. On the one hand, it does not need to use a large amount of piled materials, such as sand and stone, as preloading load, which solves the trouble of supplying preloaded materials, and on the other hand, the atmosphere Pressure is a free resource, which reduces engineering costs, especially for large-area soft-base treatments, which can greatly save engineering investment.
2) Fast consolidation and short construction period. Since the foundation does not undergo shear deformation under the action of vacuum pressure, no matter the degree of vacuum during the loading process, the foundation will not be unstable when applied once. With the maturity of vacuum preloading reinforcement technology in China, the vacuum degree under the film can reach about 85 kPa. Although the speed of consolidation does not depend on the magnitude of the preloading load, the overload is greater when the load is equal. The speed of residual settling must be faster. Since the load of the vacuum preload is large and the loading process is fast, the reinforcement time is short.
3), The construction is simple, the vacuum preloading is achieved by pumping air, then the unloading can be stopped as long as the pumping is stopped, that is, there is no problem that a large amount of unloading sand needs to be treated, which is in areas with poor external traffic conditions, It looks very good. In addition, vacuum preloading does not require the use of a large number of construction machines during loading, construction disturbance is small, construction accidents are not easy to occur, and after the required vacuum is stably maintained, the remaining work is only daily inspection and maintenance.
4), The reinforcement effect is good, the degree of consolidation of the vacuum preload can reach more than 90%, which can eliminate most of the settlement of the foundation. Moreover, since the atmospheric pressure is evenly distributed throughout the reinforced zone, the vertical deformation of the soil is also uniform throughout the reinforced zone (constrained by the surrounding soil, and the settlement at the boundary of the reinforced zone is slightly smaller), so The vacuum preloading strengthens the soft foundation, and the uneven settlement of the site will be smaller.
For sites with large ground design loads, such as container yards, if the preloading scheme is used, when the treatment area is large, the amount of earthwork used for the loading will be very amazing. Due to the impact of the stacking process, the construction period will be It has become very amazing. Due to the impact of the stacking process, the construction period will become very long. For example, in a project in Nansha, Guangzhou, the disposable treatment area is 1.50*10~5 square meters. If the preloading scheme is used, the purchased heap is required. Load sand 4*40~5 cubic meters, then divide the treatment area into three large blocks and use the piled sand in stages. The required construction period is not less than 2 years, and the construction cost reaches 400 million yuan. In the case of increasingly tight supply of sand and gravel resources, It is very difficult to obtain such a large amount of sand in a short period of time. The handling of a large amount of unloading sand is also extremely difficult. What is more important is that even if the engineering cost and construction difficulty are aside, such a long period of time cannot be used for investors or Accepted by the owner.
Because the vacuum preloading soft soil improvement has the advantages of low cost, short construction period, saving earthwork and ensuring the reinforcing effect, the treatment of large-area deep soft soil, especially the port engineering with relatively high ground design load, has the advantage that the preloading can not be compared. As mentioned above, the Guangzhou Nansha foundation project uses the vacuum preloading scheme to not only greatly reduce the project cost, but also the total processing time is only one year. Obviously, the application prospect of vacuum preloading in the landfilling project of dredging and filling soil is Very bright.
In recent years, there are mainly two ways to reclaim land for land reclamation. One way is to open a mountain for reclamation, and the other is to make land by dredging the dredged soil. The former method is more and more damaging to the environment due to high cost, and its use is increasingly restricted by government departments. The latter method is not only low in cost, relatively environmentally friendly, but also has a short construction period. More importantly, with the increase of port construction, the landfilling of dredged soil can minimize the external throwing of dredged soil in port engineering. While greatly reducing the cost of dredging projects, the use of dredged soil as a reclamation resource, so that the dredged soil that should be discarded has a value, can be described as a multi-pronged.
Because landfilling by dredging and filling land has great advantages in both technical and economic benefits, this land reclamation method is more and more accepted by people and has been widely used in reclamation projects in coastal areas. . This land reclamation method also brings greater application prospects to vacuum pre-loading foundation treatment technology.
The application prospect of vacuum pre-loading in land reclamation
The purpose of reclamation is to provide land areas that can be used for economic construction. If the site is to meet the requirements of use, ground treatment must be carried out. Vacuum preloading is widely used in large reclamation projects because the technology has the following characteristics:
1) Save pre-compressed materials and reduce project cost. Vacuum preloading uses atmospheric pressure as the motive force for preloading. On the one hand, it does not need to use a large amount of piled materials, such as sand and stone, as preloading load, which solves the trouble of supplying preloaded materials, and on the other hand, the atmosphere Pressure is a free resource, which reduces engineering costs, especially for large-area soft-base treatments, which can greatly save engineering investment.
2) Fast consolidation and short construction period. Since the foundation does not undergo shear deformation under the action of vacuum pressure, no matter the degree of vacuum during the loading process, the foundation will not be unstable when applied once. With the maturity of vacuum preloading reinforcement technology in China, the vacuum degree under the film can reach about 85 kPa. Although the speed of consolidation does not depend on the magnitude of the preloading load, the overload is greater when the load is equal. The speed of residual settling must be faster. Since the load of the vacuum preload is large and the loading process is fast, the reinforcement time is short.
3), The construction is simple, the vacuum preloading is achieved by pumping air, then the unloading can be stopped as long as the pumping is stopped, that is, there is no problem that a large amount of unloading sand needs to be treated, which is in areas with poor external traffic conditions, It looks very good. In addition, vacuum preloading does not require the use of a large number of construction machines during loading, construction disturbance is small, construction accidents are not easy to occur, and after the required vacuum is stably maintained, the remaining work is only daily inspection and maintenance.
4), The reinforcement effect is good, the degree of consolidation of the vacuum preload can reach more than 90%, which can eliminate most of the settlement of the foundation. Moreover, since the atmospheric pressure is evenly distributed throughout the reinforced zone, the vertical deformation of the soil is also uniform throughout the reinforced zone (constrained by the surrounding soil, and the settlement at the boundary of the reinforced zone is slightly smaller), so The vacuum preloading strengthens the soft foundation, and the uneven settlement of the site will be smaller.
For sites with large ground design loads, such as container yards, if the preloading scheme is used, when the treatment area is large, the amount of earthwork used for the loading will be very amazing. Due to the impact of the stacking process, the construction period will be It has become very amazing. Due to the impact of the stacking process, the construction period will become very long. For example, in a project in Nansha, Guangzhou, the disposable treatment area is 1.50*10~5 square meters. If the preloading scheme is used, the purchased heap is required. Load sand 4*40~5 cubic meters, then divide the treatment area into three large blocks and use the piled sand in stages. The required construction period is not less than 2 years, and the construction cost reaches 400 million yuan. In the case of increasingly tight supply of sand and gravel resources, It is very difficult to obtain such a large amount of sand in a short period of time. The handling of a large amount of unloading sand is also extremely difficult. What is more important is that even if the engineering cost and construction difficulty are aside, such a long period of time cannot be used for investors or Accepted by the owner.
Because the vacuum preloading soft soil improvement has the advantages of low cost, short construction period, saving earthwork and ensuring the reinforcing effect, the treatment of large-area deep soft soil, especially the port engineering with relatively high ground design load, has the advantage that the preloading can not be compared. As mentioned above, the Guangzhou Nansha foundation project uses the vacuum preloading scheme to not only greatly reduce the project cost, but also the total processing time is only one year. Obviously, the application prospect of vacuum preloading in the landfilling project of dredging and filling soil is Very bright.
Sunday, July 21, 2019
Latest Ground Improvement Techniques and Vacuum Consolidation
Latest Ground Improvement Techniques & Vacuum Consolidation of Soft Soil:
- Vibro Compaction;
- Vacuum Consolidation;
- Preloading of soil;
- Mechanically stabilized earth structures;
- Soil nailing;
- Micro-piles;
- Grouting;
- Soil stabilization by heating or vitrification;
- Ground freezing;
- Vibro-replacement stone columns.
Following are the recent methods of ground improvement Techniques used for stabilization of the soft soil improvement:
Applications of Vacuum Consolidation of Soft Soil:
- Replace standard preloading techniques eliminating the risk of failure.
- Combine with a water preloading in scare fill area. The method is used to build large developments on thick compressible soil.
- Combine with embankment pre-load using the increased stability
Preloading or Pre-Compression of Soil for Ground Improvement:
Applications of Preloading of Soil
Applications of Preloading of Soil
- Reduce post-construction
- Settlement
- Reduce secondary compression.
- Densification
- Improve bearing capacity
Vaccum reloading has been used for many years without change in the method or application to improve soft soil properties. Preloading or pre-compression is the process of placing additional vertical stress on a compressible soil to remove pore water over time.
The pore water dissipation reduces the total volume causing settlement. Surcharging preloading is an economical method for ground improvement. However, the consolidation of the soils is time dependent, delaying construction projects making it a non-feasible alternative.
The soft soils treated are Organic silt, Varved silts and clays, soft clay, Dredged material The design considerations which should be made are bearing capacity, Slope stability, Degree of consolidation.
Subscribe to:
Posts (Atom)
Prefabricated vertical drains are commonly used materials in soft soil foundation treatment
Plastic drainage boards are commonly used materials in soft soil foundation treatment. In vacuum preloading and load preloading treatment o...

-
Vacuum preloading reinforcement mechanism The vacuum preloading method uses atmospheric pressure as a preloading load. Firstly, a la...
-
With the rapid development of our social economy, the land resources available for economic construction in the coastal areas are becoming m...
-
Plastic drainage boards are commonly used materials in soft soil foundation treatment. In vacuum preloading and load preloading treatment o...